A 420-bed annex: project management and inspection, delivered in 26 months.

We managed and inspected a 420-bed annex built next to a working hospital, with site logistics through two separate gates so hospital traffic never stopped.

The base-isolated foundation uses 312 lead-rubber bearings, each installation recorded.

+09.00

Construction programme

Stages and durations; bars scaled in months.

Excavation and shoring3 mo
Isolated foundation4 mo
RC frame11 mo
Facade8 mo
MEP and finishes11 mo
Testing and acceptance2 mo